KOM2002 Deliverables'
Status 19 November 2003

All deliverables which should have been ready at the time of the annual review are also ready now.

 
Report
Service report
Services and manuals
On time
7
4
8
1 month late
4
0
0
2 months late
2
0
0
3-8 months late
1
3
0

 

No
Deliverable title

Main contrac- tor

Contrac- tors
Date
Nature
Status
D0.1
Main project website
KTH
All
3
D+R
On time
D0.2
Project presentation
KTH
All
3
D+R
On time
D8.1
Access to the on-line translation engine
Systran
Tech.
3
D+R
Service on time
D0.3

Community Outreach and Prevention Network Requirements, Information Structure and Policies

KTH
All
5
R
On time
D1.1
Existing content evaluation
Ioannina
Med.
6
R
On time
D1.2

D5.1 Start of Service + D1.2 Test site using existing content See D5.1 below.

KTH
All
6
D
Service before time
D1.3

Quality assurance plan

ABIT
Med.
6
D
On time
D2.1

Content plan

FH NON
Med.
6
R
On time
D5.1

D5.1 Start of Service + D1.2 Test site using existing content

 

KTH
All
6
D+R
Service and manuals on time
D4.1
Monitoring, rating and logging plan
KTH
All
8
R
8 months late (living document)
D0.4
Reports for the annual review Report for the annual review 2003
Omega
All
11
R
On time
D2.2

Internal service ready for user testing

KTH
All
9
D+R
Service and manuals on time
D6.1
Preliminary exploitation and dissemination plan
NetDoktor
All
9
R
On time
D8.2
Prototype of the terminological workbench
Systran
Tech.
12
D+R
One month late
D2.3
Public service ready and running
KTH
All
12
D+R
On time
D8.3
Integration of the specialized terminologi in the existing MT language pairs
Systran
All
14
D+R
One month late
D7.1

Evaluation plan

Ioannina
Med.
14
R
One day late
D4.2
First report of stepwise refinement experience
FH NON
All
14
R
Two months late
D8.4
Final version of the terminologoical workbench
Systran
Tech.
16
D+R
On time
D7.2
First evaluation report + Statistics on Web4Health usage October 200
Ioannina
Med.
16
R
One months late
D6.2
Report of first promotion stage
KTH
C3
16
R
Two months late